This page provides step-by-step instructions on how to enter and edit Subpart P Hydrogen Production process unit information for units that are NOT monitored by a CEMS.
Step 1: Add a unit
To add a unit that is NOT monitored by a CEMS, find the HYDROGEN PRODUCTION UNITS table on the Subpart Overview page and click the link titled "ADD a Unit"
To edit a unit, click the edit icon or the Name/ID link located in the first column of the HYDROGEN PRODUCTION UNITS table
To delete a unit, click the delete icon located in the last column of the HYDROGEN PRODUCTION UNITS table
Click this link to expand
Step 2: Indicate CEMS utilization for a unit
For each process unit, confirm whether or not the unit utilizes CEMS
Note that when adding a new unit you are prompted to answer the CEMS question immediately (the answer to this question will default to “No” for units added using the “ADD a Unit” link and will default to “Yes” for units added using the “ADD a Unit Monitored by CEMS” link)
The CEMS response may be changed here and the unit information will be relocated to the appropriate table on the Subpart Overview page
When finished, click SAVE
Click this link to expand
Step 3: Enter required information for a unit
For each process unit NOT monitored by a CEMS, report the following required information:
- A unique name or identifier for the unit, plus optional description for this unit (see also About Unique Unit Names) [98.166(b)(1)]
- The quantity of hydrogen produced (in metric tons) [98.166(b)(3)]
- The quantity of ammonia produced (in metric tons) [98.166(b)(4)]
- The quantity of methanol produced, if not reported under subpart X (in metric tons [98.166(e)]*
- The name and type (solid, liquid, or gaseous) of each fuel or feedstock consumed in the unit [98.166(b)(7)]
- The annual quantity of each fuel or feedstock consumed in the unit [98.166(b)(7)]*
*Required for RY2014 and later only
To add a fuel or feedstock for a unit, find the FUELS AND FEEDSTOCKS table on the Add/Edit a Unit page and click the link titled "ADD a Fuel or Feedstock"
To edit a fuel or feedstock, click the edit icon or the Name/ID link located in the first column of the FUELS AND FEEDSTOCKS table
To delete a fuel or feedstock, click the delete icon located in the last column of the FUELS AND FEEDSTOCKS table
Click this link to expand
For each fuel or feedstock used in a unit, enter a name, type and annual quantity consumed in metric tons (see also About Unique Unit Names)
When you are finished entering fuel/feedstock information, click SAVE to return to the Add/Edit a Unit page
Click this link to expand
Step 4: Save entered data for a unit
When you are finished entering all information for a unit, click SAVE to return to the Subpart Overview page
Step 5: Repeat Steps 1-4
Repeat Steps 1-4 until all process units NOT monitored by a CEMS have been added for your facility
See Also
Screen Errors
Using e-GGRT to Prepare Your Subpart P Report for RY2014 and Later
Subpart P Summary Information for this Facility for All Reporting Years
Subpart P Process Unit Information for Units NOT Monitored by CEMS for All Reporting Years
Subpart P Process Unit Information for Units Monitored by CEMS for All Reporting Years
Subpart P Emissions Information for Process Units NOT Monitored by CEMS for RY2014 and Later
Subpart P Entering Equation Inputs Using IVT
Using Subpart P Calculation Spreadsheets
Subpart P Emissions Information for Process Units Monitored by CEMS for All Reporting Years
Subpart Validation Report