Q548. For AGR vents, Option 3, the MRR says a meter must be installed, but then says in the next sentence that engineering calculations may be used if a meter is not installed - this is unclear on whether or not a meter is required

A548. The rule requires the use of a meter if one is in place. If a continuous flow meter is not already in place, then reporters have the choice of installing a continuous flow meter or alternatively using an engineering calculation to estimate the flow rate; please see §98.233(d)(5).

Wiki Markup
{show-to:group=confluence-Users}{center}{_}Footer / References Bar which is Visible to the public{_}{center}{show-to}

Panel

Updated on

Page info
modified-date
modified-date
dateformatdd/MM/YY HH:mm

Wiki Markup
{show-to:group=confluence-Users}
{info}
Source: EPA, Frequently Asked Questions, Petroleum and Natural Gas Systems, July 2011, [http://www.epa.gov/climatechange/emissions/downloads11/documents/Subpart-W-additional-faq.pdf]. Updated to reflect a continuous flow meter

Approval / Publishing History: Version 1, Approved by M. Eaddy, 6/4/2012

Expiration : none

Relevant Subpart: W, Acid Gas Removal
{info}{center}{_}History Panel For Internal Use - Not Visible to the Public{_}{center}{show-to}

This web site is maintained by a contractor to the U.S. Environmental Protection Agency (RY2021.R.02)