This topic provides a step-by-step description of how to enter Subpart Y summary information about this facility.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG1}
Click image to expand

Wiki Markup
{cloak:id=PNG1|
Cloak
cloak.toggle.zonetrue
idPNG1
cloak.toggle.type
none

Updating Summary Information for this Facility

=none|cloak.toggle.zone=true}
Panel

Image Added

Wiki Markup
{cloak}

Updating Summary Information for this Facility

Excerpt

To update Subpart Y Summary Information for this Facility, locate the FACILITY-LEVEL EMISSIONS SUMMARY table on the Subpart Y Overview page, and click OPEN for the appropriate section.

...

Petroleum Refineries must specify a CH4 calculation method for uncontrolled blowdown systems, if any. Blowdown systems where the uncondensed gas stream is routed to a flare or similar control device is considered to be controlled.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG2}
Click image to expand

zonenone
Wiki Markup
{cloak
:id=PNG2|cloak.toggle.
true
idPNG2
cloak.toggle.type
type=none|cloak.toggle.zone=true}
Panel

Image Added

Wiki Markup
{cloak}
Step 1: Select Estimation Method

...

When you are finished, click NEXT.

If "This “This facility does not have any uncontrolled blowdown systems" systems” is selected then no further data is collected for uncontrolled blowdown systems.

Depending on which methodology you choose, follow either Step 2a or Step 2b.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG3}
Click image to expand

true
Wiki Markup
{cloak:id=PNG3|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG3
cloak.toggle.type
Step 2a: Equation Y-20 Summary and Result

The annual CH4 emissions from blowdown systems is required. The e-GGRT system provides links to optional worksheets that may be used to perform the calculations; use of the spreadsheet is entirely optional and is provided for your assistance. To calculate this value using the optional spreadsheet, download the spreadsheet by clicking the link titled "Use “Use Y-20 spreadsheet to calculate"calculate”. Fill in the spreadsheet using the instructions in the spreadsheet. After completing the spreadsheet, copy the value of CH4 calculated by the spreadsheet to this page in the box next to "Annual “Annual CH4 emissions from blowdown systems (metric tons)".

The Equation Y-20 Summary is presented on the page. You can hover over an element in the equation to reveal a definition of that element.

...

The annual CH4 emissions from blowdown systems is required. The e-GGRT system provides links to optional worksheets that may be used to perform the calculations; use of the spreadsheet is entirely optional and is provided for your assistance. To calculate this value using the optional spreadsheet, download the spreadsheet by clicking the link titled "Use “Use Y-19 spreadsheet to calculate"calculate”. Fill in the spreadsheet using the instructions in the spreadsheet. After completing the spreadsheet, copy the value of CH4 calculated by the spreadsheet to this page in the box next to "Annual “Annual CH4 emissions from blowdown systems (metric tons)".

The Equation Y-19 Summary is presented on the page. You can hover over an element in the equation to reveal a definition of that element.

...

Petroleum Refineries must specify the method used to calculate the reported equipment leak emissions.

...

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG4}
Click image to expand

true
Wiki Markup
{cloak:id=PNG4|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel
idPNG4
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}
Step 1: Select Estimation Method

...

The annual CH4 emissions from equipment leaks is required. The e-GGRT system provides links to optional worksheets that may be used to perform the calculations; use of the spreadsheet is entirely optional and is provided for your assistance. To calculate this value using the optional spreadsheet, download the spreadsheet by clicking the link titled "Use “Use Y-21 spreadsheet to calculate"calculate”. Fill in the spreadsheet using the instructions in the spreadsheet. After completing the spreadsheet, copy the value of CH4 calculated by the spreadsheet to this page in the box next to "Annual “Annual CH4 emissions from equipment leaks (metric tons)."

The Equation Y-21 Summary is presented on the page. You can hover over an element in the equation to reveal a definition of that element.

Step 2b: Process-specific Methane Composition Data Method Summary and Result

If the "Use “Use process-specific methane composition data and any of the emission estimation procedures provided in the Protocol for Equipment Leak Emissions Estimates" Estimates” option was selected then the following screen will display.

...

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG5}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG5|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG5
cloak.toggle.type

Enter process-specific methane composition data (from measurement data or process knowledge) and any of the emission estimation procedures provided in the Protocol for Equipment Leak Emissions Estimates (EPA-453/R-95-017, NTIS PB96-175401).

...

Petroleum Refineries must specify the cumulative annual methane emissions (in metric tons of each pollutant emitted) for loading operations.loading operations.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG6}
Click image to expand

id
Wiki Markup
Cloak
{cloak:id=PNG6|cloak.toggle.type=none|cloak.toggle.zone
=true}
Panel

Image Added

none
Wiki Markup
{cloak}
PNG6cloak.toggle.type
Step 1: Loading Operations Emissions Information

The cumulative CH4 emissions for loading operations is required. Enter the value of CH4 in the box next to "Cumulative “Cumulative CH4 emissions for loading operations (metric tons)".

Step 2: Vessels

Complete the applicable Vessels sections for vessels with materials containing a vapor-phase CH4 concentration of at least 0.5 percent.

Click the link titled "ADD a Vessel Type".

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG7}
Click image to expand

true
Wiki Markup
{cloak:id=PNG7|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG7
cloak.toggle.type

Specify the type of vessel:

...

Click the link titled "ADD a Material" while adding or editing a Vessel type.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG8}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG8|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel
idPNG8
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}

Specify the type of material:

...

Subpart Y requires you to report whether or not your facility received and stored unstabilized crude oil during the reporting year by selecting one of the following two options:

  • "The “The facility did receive unstabilized crude oil during the reporting year.""The
  • “The facility did not receive any unstabilized crude oil during the reporting year."

Subpart Y requires you to report whether or not your facility received and stored liquids other than unstabilized crude oil during the reporting year by selecting one of the following two options:

  • "The “The facility did receive stored liquids other than unstabilized crude oil during the reporting year.""The
  • “The facility did not receive stored liquids other than unstabilized crude oil during the reporting year."

When finished, click NEXT

...

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG9}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG9|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel
idPNG9
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}
Step 2: Indicate emissions calculation methods (if applicable)

If the facility indicates use of "unstabilized “unstabilized crude oil" oil” storage tanks, Subpart Y requires you to report:

...

If the facility indicates use of "stored “stored liquids other than unstabilized crude oil" oil” storage tanks, Subpart Y requires you to report:

...

When finished, click NEXT

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG10}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG10|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG10
cloak.toggle.type
Step 3: Enter emissions information and additional data

If the facility indicates use of "unstabilized “unstabilized crude oil" oil” storage tanks, Subpart Y also requires you to report:

  • The annual CH4 emissions from unstabilized crude oil storage (from tank-specific methane composition data and direct measurement of gas generation rate or the output of Equation Y-23, in metric tons)
  • The basis for the average mole fraction of CH4 in vent gas
    • Equation Y-23 default
    • Measurement data
    • Product knowledge
    • Other (specify)
  • If the facility indicates use of "unstabilized “unstabilized crude oil" oil” storage tanks AND if the facility selected the 'tank‘tank-specific methane composition data' data’ method, the system shall require the facility to report:
    • The method used to measure tank-specific methane composition in the vapor
      • Measurement data
      • Product knowledge
      • Other (specify)
      • If measured, the number of hours missing data procedures were used
    • The method used to measure the gas generation rate
      • Procedures specified by flow meter manufacturer
      • Method published by a consensus-based standards organization
    • If measured, number of hours missing data procedures were used to measure the gas generation rate

For assistance in calculating process CH4 emissions from unstabilized crude oil storage using Equation Y-23, access the optional calculation spreadsheet by clicking the link located below the red emissions entry box titled "Use “Use Y-23 spreadsheet to calculate" calculate” and follow the provided instructions.

If the facility indicates use of "stored “stored liquids other than unstabilized crude oil" oil” storage tanks, Subpart Y also requires you to report:

...

For assistance in calculating process CH4 emissions from stored liquids other than unstabilized crude oil using Equation Y-22, access the optional calculation spreadsheet by clicking the link located below the red emissions entry box titled "Use “Use Y-22 spreadsheet to calculate" calculate” and follow the provided instructions.

...

After you save the data on this page, the next time you open the page, the calculator on the top of the page will display the CH4 emissions for stored liquids other than unstabilized crude oil and unstabilized crude oil storage, rounded to the nearest 0.01 of a metric ton. The value displayed is for informational purposes only.

...

.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG11}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG11|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG11
cloak.toggle.type

Updating Sour Gas Sent Off-Site

...

Subpart Y requires you to report whether or not your facility sent a sour gas stream off-site for sulfur recovery during the reporting year by selecting one of the following two options:

  • Yes
  • No

When finished, click NEXT, click NEXT

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG12}
Click image to expand

id
Wiki Markup
Cloak
{cloak:id=PNG12|cloak.toggle.type=none|cloak.toggle.zone
=true}
Panel

Image Added

none
Wiki Markup
{cloak}
PNG12cloak.toggle.type
Step 2: Enter emissions information and additional data (if applicable)

...

  • The annual CO2 emissions from sour gas sent off-site (the output of Equation Y-12, in metric tons)
  • If measured, specific consensus-based standard method or describe the procedure specified by the flow meter manufacturer used to measure annual volume of sour gas fed (from the facility to the off-site sulfur recovery plant)
  • If measured, the number of hours missing data procedures were used for annual volume of sour gas fed (from the facility to the off-site sulfur recovery plant)
  • If measured, the method used to measure the annual average mole fraction of carbon in the sour gas:
    • Method 18 at 40 CFR part 60, appendix A-6
    • ASTM D1945-03
    • ASTM D1946-90 (Reapproved 2006)
    • GPA 2261-00
    • UOP539-97
    • ASTM D2503-92 (Reapproved 2007)
    • Chromatographic analysis: manufacturer's manufacturer’s instructions
    • Other (specify)
  • If measured, the number of hours missing data procedures were used for annual average mole fraction of carbon in the sour gas

For assistance in calculating process CH4 emissions from sour gas sent off-site using Equation Y-12, access the optional calculation spreadsheet by clicking the link located below the red emissions entry box titled "Use “Use Y-12 spreadsheet to calculate" calculate” and follow the provided instructions.

...

After you save the data on this page, the next time you open the page, the calculator on the top of the page will display the CO2 emissions for sour gas sent off-site, rounded to the nearest 0.1 of a metric ton. The value displayed is for informational purposes only.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG13}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG13|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel
idPNG13
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}

Updating Delayed Coking

Petroleum refineries must report the cumulative CH4 emissions from all delayed coking units at the facility.

...

  • The cumulative CH4 emissions from all delayed coking units at the facility
  • For each coking drum set at your facility, Subpart Y also requires you to report
    • A unique unit name or identifier and an optional description or label (see also About Unique Unit Names)
    • The number of coking drums in the set
    • The basis for the mole fraction of methane in the coking gas
    • The basis for the volumetric void fraction of the coke vessel prior to steaming
Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak:id=PNG14}
Click image to expand
Image Added

unmigrated-inline-wiki-markup
{cloak

...

:id

...

true
Cloak
=PNG14|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel
idPNG14
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}

To add a coking drum set, click the link titled "ADD a Coking Drum Set" below the COKING DRUM SETS table, enter the required information, then click SAVE. Repeat for each coking drum set at your facility.

...

.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG15}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG15|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG15
cloak.toggle.type
Step 2: Save Your Data

When you have finished entering all delayed coking unit emissions information and additional data, click SAVE.

After you save the data on this page, the next time you open the page, the calculator on the top of the page will display the cumulative CH4 emissions from all delayed coking units at the facility, rounded to the nearest 0.01 of a metric ton. The value displayed is for informational purposes only..

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG16}
Click image to expand

true
Wiki Markup
{cloak:id=PNG16|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG16
cloak.toggle.type

#Back to Top

See Also

Screen Errors
Using e-GGRT to Prepare Your Subpart Y Report
Subpart Y Summary Information for this Facility
Subpart Y Delayed Coking Unit Information
Subpart Y Asphalt Blowing Unit Information
Subpart Y Coke Calcining Unit Information
Subpart Y Catalytic Cracking, Fluid Coking, and Catalytic Reforming Unit Information
Subpart Y Flares Unit Information
Subpart Y Process Vents Unit Information
Subpart Y Sulfur Recovery Plant Information
Subpart Y Emissions Information for Process Units Monitored by CEMS
Subpart Validation Report

This web site is maintained by a contractor to the U.S. Environmental Protection Agency (RY2023.R.01)