Action |
---|---|
February 1 |
Due date for electric power entities to register specified facilities outside California |
April 10 |
Reporting deadline for facilities and suppliers of fuels and carbon dioxide, except when subject to abbreviated reporting |
June 1 |
Reporting deadline for electric power entities and those subject to abbreviated reporting |
July 15 |
Deadline for corrections to RPS Adjustment data required in electric power entity reports |
August 20 |
Notification deadline of potential adverse verification statement to reporting entity by verification team |
August 31 |
Last day to file a petition to ARB that contests the final verification statement as determined by the verification team |
September 1 |
Final verification statement deadline. All adverse emissions data verification statements are subject to ARB assigning their emissions level for their compliance obligation in the cap and trade program. |
October 10 |
Completion deadline for all petitions filed to ARB and determinations of assigned emissions levels |