Q73. If a non-Acid Rain unit combusts coal or other solid fossil fuel and has gas monitors installed but does not have a stack flow monitor, is installation and certification of a stack flow monitor required?

A73.  If the unit and the currently installed gas monitors meet all six conditions specified in §98.33(b)(4)(ii), then the Tier 4 methodology must be used, and a flow monitor must be installed and certified prior to the applicable deadline specified in §98.33(b)(5). (See §98.34(c).) 


Show If
special@authenticated

Footer / References Bar which is Visible to the public

Panel

Updated on on 

Page info
modified-date
modified-date
dateformatdd/MM/YY HH:mm

Wiki Markup
{show-to:group=confluence-Users}{_}Footer / References Bar which is Visible to the public{_}{show-to}

...

Show If
special@authenticated
Info

Source: This question and answer was derived from a Legacy FAQ, revised by D. Richards,

...

11/14/2011

...

.

Approval

...

/

...

Publishing

...

History:

...

Version

...

1,

...

approved

...

by

...

M.

...

Hannan,

...

1/23/2103

...

.

Expiration:

...

none

...

Relevant

...

Subpart: Subpart C


History Panel For Internal Use - Not Visible to the Public