Q809. What are the current BAMM provisions for reporting year 2015?

...

A809. On November 25, 2014 the EPA finalized revisions to Subpart W of the GHGRP, including changes to various calculation methods, monitoring requirements, and data reporting provisions (http://www.gpo.gov/fdsys/pkg/FR-2014-11-25/pdf/2014-27681.pdf).Background

Who can use BAMM in 2015?

...

 

 

 
Industry SegmentEmission Source TypeTypes of Data Covered
Onshore petroleum and natural gas productionWell Venting for Liquids UnloadingVented natural gas flow rate for any well in a unique tubing diameter group and pressure group combination that has not previously been measured when using calculation method 1 as prescribed in 98.233(f)(1) if calculation method 1 was used in calendar year 2014 and will be used again in 2015
Gas Well Venting during Completions and Workovers with Hydraulic FracturingIf using Equation W-10A, initial and average flowback rates when using calculation method 1 in 98.233(g)(1)(i) or pressures upstream and downstream of the choke when using calculation method 2 in 98.233(g)(1)(ii) for any well in a well type combination that has not been previously measured
Onshore natural gas processing




Reciprocating Compressors                                          

Centrifugal Compressors  



Reciprocating Compressors

As found measurements of manifolded emissions from groups of reciprocating compressor sources according to 98.233(p)(4) and (5).

Centrifugal Compressors

As found measurements of manifolded emissions from groups of centrifugal compressor sources according to 98.233(o)(4) and (5).

  
Onshore natural gas transmission compression
Underground natural gas storage
Liquefied natural gas (LNG) storage
LNG Import and Export Equipment

...

As the provisions covering which monitoring and measurement requirements are eligible for BAMM have changed substantially since the original 2015 BAMM requests were submitted, the EPA is requiring that any facility that wants to use BAMM beyond March 31, 2015 must reapply using the revised BAMM module in e-GGRT.  The EPA will distribute official notifications to facilities who submitted a BAMM request under the previous set of requirements once the rule takes effect in January 2015. 


Show If
special@authenticated
Footer / References Bar which is Visible to the public
Panel

Updated on

Page info
infoTypemodified-Modified date
typemodified-dateFlat
dateformatdd/MM/YY HH:mm

Show If
special@authenticated
Info

Source: Akachi Imegwu,

Wiki Markup
{show-to:group=confluence-Users} {info} Source: Akachi Imegwu,

12/17/2014

.

Approval

/

Publishing

History:

Version 1

Version 1

Expiration:

None

Relevant Subpart/Component: Subpart W BAMM {info}{_}History Panel For Internal Use - Not Visible to the Public{_}{show-to}

Relevant Subparts: Subpart W BAMM.