Q85.
...
Is
...
the
...
use
...
of
...
Subpart
...
C
...
tiers
...
required
...
after
...
2010
...
and
...
is
...
it
...
acceptable
...
to
...
use
...
the
...
best
...
available
...
monitoring
...
provisions
...
under
...
Subpart
...
A
...
beyond
...
2010?
...
A85. Yes, the use of Subpart C Tiers is required after 2010. The use of best available monitoring methods as described in Subpart A may not be extended beyond the end of 2010 except for units subject to subpart P (Hydrogen Production), subpart X (Petrochemical Production), or subpart Y (Petroleum Refineries). Note that there may be subpart specific BAMM requirements not included in subpart A-. Note, however, that this timing does not apply to subpart-specific BAMM requirements-. (See §98.3(d)(2)(iii) and §98.3(j).)
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
Updated on
|
Wiki Markup |
---|
{show-to:group=confluence-Users}{center}{_}Footer / References Bar which is Visible to the public{_}{center}{show-to} |
...
Wiki Markup |
---|
{show-to:group=confluence-Users} {info} Source: This question and answer was derived from a Legacy FAQ, revised by M. Hannan, 1/23/2013 Approval / Publishing History: Version 2, approved by L. Grogan-McCulloch, 2/13/2013 Expiration: none Relevant Subparts: Subpart C {info}{center}{_}History Panel For Internal Use - Not Visible to the Public{_}{center}{show-to} |