Subpart Q Process Unit Information for Units NOT Monitored by CEMS
Note: The Cal e-GGRT help system includes general instruction on using the California GHG reporting tool. However, the help system may not explain differences between California and U.S. EPA reporting requirements. Please refer to the ARB reporting website for California-specific reporting requirements and additional help.

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 4.0

...

To delete a process unit, click the delete icon or red "x" “x” located in the last column of the table.

Wiki Markup
{composition-setup}{composition-setup}

Wiki Markup
{toggle-cloak
:id
=PNG1}
Click image to expand

true
Wiki Markup
{cloak:id=PNG1|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG1
cloak.toggle.type

Step 2: Indicate CEMS utilization for the process unit

...

Note

Note that when adding a new process unit you are prompted to answer the CEMS question immediately (the answer to this question will default to "No" “No” for process unit added using the "ADD “ADD a Unit" Unit” link and will default to "Yes" “Yes” for units added using the "ADD “ADD a CEMS Unit" Unit” link).

The CEMS response may be changed here and the process unit information will be relocated to the appropriate table on the Subpart Overview page.

When finished, click SAVE.

Wiki Markup
{toggle-cloak
:id
=PNG2}
Click image to expand

true
Wiki Markup
{cloak:id=PNG2|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel
idPNG2
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}

Step 3: Select calculation methodology

...

When finished, click SAVE.

Wiki Markup
{toggle-cloak
:id
=PNG3}
Click image to expand

true
Wiki Markup
Cloak
{cloak:id=PNG3|cloak.toggle.type=none|cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG3
cloak.toggle.type

Step 4: Define the process unit

...

To add an input or an output, click "Add an Input" or "Add an Output" below each respective table.

Wiki Markup
{toggle-cloak
:id
=PNG4}
Click image to expand

true
Wiki Markup
{cloak:id=PNG4|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG4
cloak.toggle.type

For each input or output associated with the process unit, Subpart Q requires you to report the following information:

...

When you are finished entering the required information for an input or output, click SAVE. Note, if you are using the carbon mass balance method, you must identify inputs and outputs associated with each process. If you do not, as a reminder you will see a data completeness validation message on the Validation report page as a reminder that you have not completed Unit-Level data entry.

Wiki Markup
{toggle-cloak
:id
=PNG5}
Click image to expand

true
Wiki Markup
{cloak:id=PNG5|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel
idPNG5
cloak.toggle.typenone

Image Added

Wiki Markup
{cloak}

Repeat this step until all inputs and outputs associated with the process unit have been added and defined, then proceed to Step 6.

...

When you are finished entering all required information for the process unit, click SAVE.

Wiki Markup
{toggle-cloak
:id
=PNG6}
Click image to expand

true
Wiki Markup
{cloak:id=PNG6|cloak.toggle.type=none|
Cloak
cloak.toggle.zone=true}
Panel

Image Added

none
Wiki Markup
{cloak}
idPNG6
cloak.toggle.type

Step 7: Repeat Steps 1-6

Repeat Steps 1-6 until all process units NOT monitored by CEMS have been added for your facility.

...