Note: The Cal e-GGRT help system includes general instruction on using the California GHG reporting tool. However, the help system may not explain differences between California and U.S. EPA reporting requirements. Please refer to the ARB reporting website for California-specific reporting requirements and additional help.

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Anchor
Back to Top
Back to Top

This page provides a description of how to enter Subpart H Cement Production summary information for this facility.

Adding or Updating Summary Information for this Facility

To add or update summary information for this facility, locate the SUBPART H SUMMARY INFORMATION FOR THIS FACILITY table on the Subpart Overview page and click OPEN.

Composition Setup

Toggle Cloak
idPNG1
Click image to expand

Cloak
cloak.toggle.zonetrue
idPNG1
cloak.toggle.typenone

Subpart H requires you to report the following data about your facility:

  • Annual CO2 process emissions from cement manufacturing (short tons)
  • Annual cement production for the facility (tons)
  • The total number of kilns at the facility
  • The total number of operating kilns

In addition, ยง95110(d) requires you to report the following data about your facility:

  • Annual clinker production for the facility (tons)
  • Annual clinker consumed by the facility (tons)
  • Annual limestone consumed for blending (tons)
  • Annual gypsum consumed for blending (tons)
  • Annual cement substitute consumed by the facility

For assistance in calculating CO2 process emissions from cement production, access the calculation spreadsheets for this subpart by clicking the link located below the red emissions data entry box titled "Use Subpart H equation spreadsheets to calculate," then follow the provided instructions. When you have completed the spreadsheet use the EQUATION SPREADSHEET ATTACHMENTS space at the bottom of the page to upload your saved spreadsheet.

When you have entered the required information, click SAVE. You will then be directed back to the Subpart Overview page to complete entering any other required data.

Toggle Cloak
idPNG2
Click image to expand

Cloak
cloak.toggle.zonetrue
idPNG2
cloak.toggle.typenone

#Back to Top

See Also

Screen Errors
Using Cal e-GGRT to Prepare Your Subpart H Report
Subpart H Kiln Information for Kilns NOT Monitored by CEMS
Subpart H Kiln Information for Kilns Monitored by CEMS
Subpart H Emissions Information for Kilns NOT Monitored by CEMS
Subpart H Emissions Information for Kilns Monitored by CEMS